10 am - 10.30 am Meeting with team leads
The following was discussed :
1) Sound level will be completed by 5 pm today
2) Light node assets will be completed by the Production team
3) Sound level color change to black and white
4) Level 1 completed by 5 pm Thursday the 7th of May
5) Level 2 completed by 5 pm Monday the 11th of May
The Production timeline has been updated.
12 noon - 12.15 pm Simon's meeting with Chris regarding the launch
The following was discussed :
1) Whom to invite ?
2) Do we want random people to walk in or do we stick to invitees only ?
3) Money
4) Venue
Day 18 - 7/05
6.30 - 8.15 Meeting with executive producers
The following was discussed :
1) See that the existing concept does not change towards the end of production.
2) Implement, review and reassign tasks to redo stuff.
3) Executive meeting change for next week. The meetings will be held on Tuesday and Friday.
4) Turn down the scrolling texture as it is distracting.
5) Make the mesh of space opaque.
6) 50% transparency on wall textures.